Project Schedule


The following table shows the planned project schedule.

 

EA and Preliminary Engineering
(Rabbit Creek Road to 36th Ave)
2004 - 2007
Public Involvement 2004 - 2007 / 2016 - 2020
Design Study Report Summer 2016 - Spring 2018
Plans, Specifications, and Estimates Winter 2017 - Winter 2020
Right-of-Way Appraisal,
Acquisition & Relocation
Spring 2019 - Winter 2020
Construction 2021 - 2024*

                    
*Depends upon availability of funding.